The TF2000 light SCULFORT Underfloor wheel lathe and Telecontrolled Railroad Shunter that we sent to Fuzhou Metro Line 2, completed installation and commissioning on September 10, 2018, and passed acceptance on September 12, to meet the upcoming official on-line operation.
This group of equipment began installation on August 4, which only took 39 days from installation to acceptance, and it only took 2 days from completion to acceptance, That allowed us to create a new record of fast and high efficiency in the industry.
Our service team has undergone professional training and assessment, so that we strictly control the quality of products and the efficiency and stability of equipment operation. Besides, we always insisting on providing excellent service experience for every customer who chooses us.